Filter by category
Filter by Date
[EventId:202504101725_review] Prices for interval 10-Apr-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101720_review] Prices for interval 10-Apr-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101715_review] Prices for interval 10-Apr-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101710_review] Prices for interval 10-Apr-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_review] Prices for interval 10-Apr-2025 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101700_review] Prices for interval 10-Apr-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025
Refer Market Notice 126468
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1520 hrs 10/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 11/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Release of PEC-1 and combined V-SA limits - 11 April 2025
Refer to market notice 123956
AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.
The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.
With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations