[EventId:202506061800_review] Prices for interval 06-Jun-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061755_review] Prices for interval 06-Jun-2025 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061750_review] Prices for interval 06-Jun-2025 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061745_review] Prices for interval 06-Jun-2025 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061740_review] Prices for interval 06-Jun-2025 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506061735_review] Prices for interval 06-Jun-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 6 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Jun-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Completed - CHG0103213 - Scheduled maintenance of Marketnet router in Brisbane
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Initial - CHG0103273 - Scheduled Maintenance on Brisbane Datacentre
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Scheduled Maintenance on Brisbane Datacentre
Change Start Date & Time: 14/06/2025 10:00:00
Change End Date & Time: 14/06/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - A brief interuption of up to 60 seconds while services are failed over from QLD to NSW Datacenter.
Lan-2-Lan VPN Participants (IPSEC) - Up to 4 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN's or 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10 or 202.44.78.12) prior to this scheduled outage. *** Failure to do so will impact connectivity to Marketnet Services ***.
B2B VPN - No impact is expected.
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127412
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 06/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1900 hrs 06/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/06/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.