117725INTER-REGIONAL TRANSFER20/08/2024 09:28:20 AM

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

A planned outage of Kerang to Wemen 220kV line in the VIC region was scheduled from 0600 hrs 20/08/2024 to 1930 hrs 20/08/2024.

The outage has been completed and Kerang to Wemen 220kV line returned to service at 0925 hrs 20/08/2024

Constraint set revoked: V-KGWT

Manager NEM Real Time Operations
     
117724INTER-REGIONAL TRANSFER19/08/2024 09:54:20 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 2155 hrs 19/08/2024

I-MURRAYLINK

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1,VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
117677INTER-REGIONAL TRANSFER14/08/2024 04:22:12 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1620 hrs 14/08/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
117672INTER-REGIONAL TRANSFER14/08/2024 11:08:17 AM

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

At 1006 hrs 14/08/2024 there was a short notice outage of CollectorWF-Marulan 4 330kV LINE.

The following constraint set(s) invoked at 1000 hrs 14/08/2024
N-CTMN_4_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117669INTER-REGIONAL TRANSFER14/08/2024 08:05:49 AM

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

A planned outage of Collector - Marulan No 4 330kV Line in the NSW region was scheduled from 0800 hrs 14/08/2024 to 1700 hrs 02/09/2024.


The outage has been cancelled.

Constraint set(s) invoked: N-CTMN_4_WG_CLOSE


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117562RESERVE NOTICE05/08/2024 07:17:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117561 is cancelled at 1915 hrs 05/08/2024.

Manager NEM Real Time Operations
     
117561RESERVE NOTICE05/08/2024 06:21:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117548 has been updated at 1815 hrs to the following:

[1.] From 1930 hrs 05/08/2024 to 2130 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 386 MW.

Manager NEM Real Time Operations
     
117547RESERVE NOTICE05/08/2024 04:27:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.

Manager NEM Real Time Operations
     
117546INTER-REGIONAL TRANSFER04/08/2024 10:56:12 AM

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.

The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
     