126311SETTLEMENTS RESIDUE04/04/2025 08:15:24 PM

[EventId:202504042015_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 20:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2015 hrs on 4 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Refer to market notice: 126310

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2015 hrs on 4 April 2025.

This is an AEMO autogenerated Market Notice.
     
126310SETTLEMENTS RESIDUE04/04/2025 07:15:23 PM

[EventId:202504041915_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 19:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1915 hrs on 4 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1915 hrs on 4 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126309SETTLEMENTS RESIDUE04/04/2025 06:30:30 PM

[EventId:202504041830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Refer to market notice: 126297

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 4 April 2025.

This is an AEMO autogenerated Market Notice.
     
126297SETTLEMENTS RESIDUE04/04/2025 05:05:15 PM

[EventId:202504041705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 4 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 4 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126291MARKET SYSTEMS04/04/2025 03:33:34 PM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025


During the window,FPP calculations may be delayed at various points.


Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126281NON-CONFORMANCE04/04/2025 01:15:15 PM

NON-CONFORMANCE Region SA1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ADPBA1
Duration: 04/04/2025 12:30 to 04/04/2025 13:15
Amount: -6 MW
Constraint: NC-S_ADPBA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126275MARKET SYSTEMS04/04/2025 09:23:36 AM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00

Environment: Pre-Production

Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126269NON-CONFORMANCE04/04/2025 06:20:15 AM

NON-CONFORMANCE Region QLD1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 04/04/2025 05:55 to 04/04/2025 06:20
Amount: 77 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126264NON-CONFORMANCE04/04/2025 04:55:19 AM

NON-CONFORMANCE Region NSW1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 04/04/2025 04:45 to 04/04/2025 04:55
Amount: -26 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
     