117349MARKET INTERVENTION15/07/2024 04:03:12 PM

Direction - SA region 15/07/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 15/07/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 15/07/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
117348MARKET INTERVENTION15/07/2024 04:01:20 PM

Direction - SA region 15/07/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 15/07/2024

Refer to Market Notice 117347


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 15/07/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 2200 hrs 15/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 16/07/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
117347MARKET INTERVENTION15/07/2024 02:02:03 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117346

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 15/07/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 15/07/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
117346MARKET INTERVENTION15/07/2024 01:49:44 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 15/07/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
117339INTER-REGIONAL TRANSFER12/07/2024 09:00:58 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo No.1 275 kV line - SA region - 12/07/2024

A planned outage of Robertstown - Tungkillo No.1 275 kV line in the SA region was scheduled to be completed at 1730 hrs 14/07/2024.

The outage has been completed and Robertstown - Tungkillo No.1 275 kV line returned to service at 2043 hrs 12/07/2024

Constraint set(s) revoked: S-RBTU

Manager NEM Real Time Operations
     
117334INTER-REGIONAL TRANSFER10/07/2024 04:53:47 PM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

Refer AEMO Electricity Market Notice 117333

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 1655 hrs.

Manager NEM Real Time Operations
     
117333INTER-REGIONAL TRANSFER10/07/2024 04:31:32 PM

Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (VIC Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 1625 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1


Manager NEM Real Time Operations
     
117332INTER-REGIONAL TRANSFER10/07/2024 03:51:45 PM

Inter-regional transfer limit variation - Coffs Harbour - Lismore (89) 330kV line - NSW region - 10/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Coffs Harbour - Lismore (89) 330kV line - NSW region - 10/07/2024

A planned outage of Coffs Harbour - Lismore (89) 330kV line in the NSW region was scheduled to return to service 0514 hrs 12/07/2024.

The outage has been completed and Coffs Harbour - Lismore (89) 330kV line returned to service at 1540 hrs 10/07/2024

Constraint set(s) revoked: N-CHLS_89 and N-DLETS_OS

Manager NEM Real Time Operations
     
117331INTER-REGIONAL TRANSFER10/07/2024 12:24:27 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117330

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1220 hrs.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm