127438INTER-REGIONAL TRANSFER07/06/2025 08:58:31 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
     
127435RESERVE NOTICE07/06/2025 07:29:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127431PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061740_confirmed] Prices for interval 06-Jun-2025 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:40.

In accordance with Market Notice 127420 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127430PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061800_confirmed] Prices for interval 06-Jun-2025 18:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 18:00.

In accordance with Market Notice 127425 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127429PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061755_confirmed] Prices for interval 06-Jun-2025 17:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:55.

In accordance with Market Notice 127424 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127428PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061750_confirmed] Prices for interval 06-Jun-2025 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:50.

In accordance with Market Notice 127423 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127427PRICES UNCHANGED06/06/2025 06:00:20 PM

[EventId:202506061745_confirmed] Prices for interval 06-Jun-2025 17:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:45.

In accordance with Market Notice 127422 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127426PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061735_confirmed] Prices for interval 06-Jun-2025 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:35.

In accordance with Market Notice 127417 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127324INTER-REGIONAL TRANSFER28/05/2025 05:55:45 PM

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.

The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC

and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC

These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.