127516MARKET INTERVENTION12/06/2025 04:01:57 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 14/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127508NON-CONFORMANCE12/06/2025 12:10:21 AM

NON-CONFORMANCE Region VIC1 Thursday, 12 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 12 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 12/06/2025 00:05 to 12/06/2025 00:10
Amount: 14 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
127486RESERVE NOTICE09/06/2025 01:48:41 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127481 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127485RESERVE NOTICE09/06/2025 01:47:20 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127482 is cancelled at 01:15 hrs. 09/06/2025.

Manager NEM Real Time Operations
     
127482RESERVE NOTICE08/06/2025 07:25:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1800 hrs 11/06/2025 to 1900 hrs 11/06/2025.
The forecast capacity reserve requirement is 881 MW.
The minimum capacity reserve available is 856 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127481RESERVE NOTICE08/06/2025 07:24:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127480 has been updated to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 654 MW.
The minimum capacity reserve available is 608 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 905 MW.
The minimum capacity reserve available is 895 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127480RESERVE NOTICE08/06/2025 06:18:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127477 has been updated at 1815 hrs to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 619 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127477RESERVE NOTICE08/06/2025 02:24:30 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127447 has been updated at 1415 hrs to the following:

[1.] From 0600 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 728 MW.
The minimum capacity reserve available is 612 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 919 MW.
The minimum capacity reserve available is 900 MW.
AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127476MARKET INTERVENTION08/06/2025 02:25:22 PM

Cancellation - AEMO Intervention Event - SA region 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 07/06/2025

Refer to Market Notice 127455

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 08/06/2025.


Manager NEM Real Time Operations
     