Market Notices

127752RECLASSIFY CONTINGENCY23/06/2025 09:41:56 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 23/06/2025 21:41 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
127751RECLASSIFY CONTINGENCY23/06/2025 09:29:34 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible in the Mount Lofty Ranges, Upper South East, Lower South East, Adelaide Metro, Mount Lofty Ranges, Mid North and Murraylands districts because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action(s) to maintain power system security at 2130 hrs 23/06/2025

Constraint set(s) invoked: I-VS_250

Duration: until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
     
127750RECLASSIFY CONTINGENCY23/06/2025 07:49:15 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 23/06/2025 19:49 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127749RECLASSIFY CONTINGENCY23/06/2025 06:16:56 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 1810 hrs 23/06/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
127748RECLASSIFY CONTINGENCY23/06/2025 06:16:40 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Duration: 1810 hrs 23/06/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
127747MARKET INTERVENTION23/06/2025 07:09:33 PM

Cancellation - Direction - NSW region - 23/06/2025

AEMO ELECTRICITY PARTICIPANT NOTICE

Cancellation - Direction - NSW region - 23/06/2025

Refer to Market Notice 127745.

The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.

Manager NEM Real Time Operations
     
127745MARKET INTERVENTION23/06/2025 06:00:38 PM

Direction - NSW region 23/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Direction - NSW region 23/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.

A further market notice will be issued when all directions related to this requirement have been cancelled.

For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).


Manager NEM Real Time Operations
     
127740MARKET INTERVENTION23/06/2025 02:59:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127696

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/06/2025.

The direction update is issued at 1500 hrs 23/06/2025.

Manager NEM Real Time Operations
     
127728RESERVE NOTICE23/06/2025 02:23:51 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs to 0300 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 205 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm