Market Notices

126287MARKET INTERVENTION04/04/2025 02:47:45 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126249

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0130 hrs 05/04/2025.

The direction update is issued at 1445 hrs 04/04/2025.

Manager NEM Real Time Operations
     
126286MARKET INTERVENTION04/04/2025 02:47:05 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126280

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 05/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 04/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126281NON-CONFORMANCE04/04/2025 01:15:15 PM

NON-CONFORMANCE Region SA1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ADPBA1
Duration: 04/04/2025 12:30 to 04/04/2025 13:15
Amount: -6 MW
Constraint: NC-S_ADPBA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126280MARKET INTERVENTION04/04/2025 01:06:07 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 05/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126269NON-CONFORMANCE04/04/2025 06:20:15 AM

NON-CONFORMANCE Region QLD1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 04/04/2025 05:55 to 04/04/2025 06:20
Amount: 77 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126264NON-CONFORMANCE04/04/2025 04:55:19 AM

NON-CONFORMANCE Region NSW1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 04/04/2025 04:45 to 04/04/2025 04:55
Amount: -26 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126263GENERAL NOTICE04/04/2025 08:11:29 AM

Update - Vulnerable lines in Qld region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in Qld region
Refer to AEMO Electricity Market Notice 126262 and 126271
At 0152 hrs 04/04/2025 the the Ross - Townsville South No 7156 and 7249 132kV lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the the Ross - Townsville South No 7156 and 7249 132kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
126259NON-CONFORMANCE03/04/2025 07:15:20 PM

NON-CONFORMANCE Region QLD1 Thursday, 3 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 3 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 03/04/2025 19:05 to 03/04/2025 19:15
Amount: -13 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126256MARKET INTERVENTION04/04/2025 03:56:04 AM

Cancellation - AEMO Intervention Event - SA region 02/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 02/04/2025

Refer to Market Notice 126218

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 04/04/2025.


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm