127920MARKET INTERVENTION03/07/2025 06:19:48 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 04/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127914RESERVE NOTICE02/07/2025 11:36:39 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127909 is cancelled at 1134 hrs 02/07/2025.

Manager NEM Real Time Operations
     
127909RESERVE NOTICE01/07/2025 09:21:44 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127908 has been updated to the following:

[1.] From 1900 hrs 02/07/2025 to 2130 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 326 MW.

Manager NEM Real Time Operations
     
127908RESERVE NOTICE01/07/2025 07:20:50 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127906 has been updated at 1915 hrs to the following:


[1.] From 1800 hrs 02/07/2025 to 1830 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 331 MW.

[2.] From 2100 hrs 02/07/2025 to 2230 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 270 MW.


Manager NEM Real Time Operations
     
127906RESERVE NOTICE01/07/2025 02:51:08 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127903 has been updated to the following:

[1.] From 0800 hrs 02/07/2025 to 0900 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 377 MW.

[2.] From 1700 hrs 02/07/2025 to 1800 hrs 02/07/2025.
The forecast capacity reserve requirement is 455 MW.
The minimum capacity reserve available is 303 MW.

[3.] From 2130 hrs 02/07/2025 to 2230 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 272 MW.

Manager NEM Real Time Operations
     
127903RESERVE NOTICE01/07/2025 02:37:03 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127902 has been updated to the following:

[1.] From 0800 hrs 02/07/2025 to 0900 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 383 MW.

[2.] From 1800 hrs 02/07/2025 to 2200 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 283 MW.

Manager NEM Real Time Operations
     
127902RESERVE NOTICE01/07/2025 12:51:41 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Periods:


[1.] From 0700 hrs 02/07/2025 to 1030 hrs 02/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 252 MW.


[2.] From 1700 hrs 02/07/2025 to 1830 hrs 02/07/2025.
The forecast capacity reserve requirement is 455 MW.
The minimum capacity reserve available is 315 MW.


[3.] From 2100 hrs 02/07/2025 to 0130 hrs 03/07/2025.
The forecast capacity reserve requirement is 435 MW.
The minimum capacity reserve available is 265 MW.


Manager NEM Real Time Operations
     
127899RESERVE NOTICE30/06/2025 08:42:06 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127895 is cancelled at 2040 hrs 30/06/2025.

Manager NEM Real Time Operations
     
127898RESERVE NOTICE30/06/2025 05:47:01 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127897 is cancelled at 1741 hrs 30/06/2025.