Filter by category
Filter by Date
[EventId:202504101725_review] Prices for interval 10-Apr-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101720_review] Prices for interval 10-Apr-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101715_review] Prices for interval 10-Apr-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101710_review] Prices for interval 10-Apr-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_review] Prices for interval 10-Apr-2025 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504101700_review] Prices for interval 10-Apr-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 10 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126467 is cancelled at 1540 hrs 10/04/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025
NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1
Auto-generated on behalf of Manager NEM Real Time Operations
Initial - CHG0100085 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 14/04/2025 08:00:00
Change End Date & Time: 16/04/2025 19:00:00
Outage Start Date & Time: 15/04/2025 20:15:00
Outage End Date & Time: 15/04/2025 21:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities.
During the window, delivery of FPP calculations through the participant data model may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.