Filter by category
Filter by Date
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 2020 hrs 20/06/2025
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
Inter-regional transfer limit variation - Directlink No.3 Cable - NSW region - 20/06/2025
A planned outage of Directlink No.3 Cable in the NSW region was scheduled from 0700 hrs 16/06/2025 to 1700 hrs 27/06/2025.
The outage has been completed and Directlink No.3 Cable returned to service at 1210 hrs 20/06/2025
Constraint set(s) revoked: N-MBTE_1
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 20 June 2025
NON-CONFORMANCE VIC1 Region Friday, 20 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 20/06/2025 01:50 to 20/06/2025 02:10
Amount: -37 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127651 is cancelled at 1400 hrs 18/06/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 18 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 18 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/06/2025 14:25 to 18/06/2025 14:40
Amount: -55 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0600 hrs to 0800 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1420 MW.
2. From 1630 hrs to 2300 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1487 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 18/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127645 is cancelled at 1412 hrs 17/06/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127638 is cancelled at 1412 hrs 17/06/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 18/06/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127646 is cancelled at 1411 hrs 17/06/2025.
Manager NEM Real Time Operations