126373RECLASSIFY CONTINGENCY05/04/2025 11:02:02 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 05/04/2025 23:01 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
126372RECLASSIFY CONTINGENCY05/04/2025 10:37:22 PM

Cancellation of a Non-Credible Contingency Event: Ross - Townsville South No.7156 132 kV Line and Ross - Townsville South No.7249 132 kV Line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Townsville South No.7156 132 kV Line and Ross - Townsville South No.7249 132 kV Line

Cancellation time: 05/04/2025 22:35

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 126351

Manager NEM Real Time Operations
     
126371RECLASSIFY CONTINGENCY05/04/2025 10:04:40 PM

Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Cancellation time: 05/04/2025 22:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 126355

Auto-generated on behalf of Manager NEM Real Time Operations
     
126370RECLASSIFY CONTINGENCY05/04/2025 08:24:41 PM

Cancellation of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Cancellation time: 05/04/2025 20:24

Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 126354

Auto-generated on behalf of Manager NEM Real Time Operations
     
126363PRICES SUBJECT TO REVIEW05/04/2025 06:00:11 PM

[EventId:202504051805_review] Prices for interval 05-Apr-2025 18:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Apr-2025 18:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126362PRICES SUBJECT TO REVIEW05/04/2025 05:55:14 PM

[EventId:202504051800_review] Prices for interval 05-Apr-2025 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 5 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Apr-2025 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126361PRICES SUBJECT TO REVIEW05/04/2025 05:50:17 PM

[EventId:202504051755_review] Prices for interval 05-Apr-2025 17:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 5 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Apr-2025 17:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126360PRICES SUBJECT TO REVIEW05/04/2025 05:45:16 PM

[EventId:202504051750_review] Prices for interval 05-Apr-2025 17:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 5 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Apr-2025 17:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126359PRICES SUBJECT TO REVIEW05/04/2025 05:40:15 PM

[EventId:202504051745_review] Prices for interval 05-Apr-2025 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 5 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Apr-2025 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     