Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Palmerston - Hadspen 3 & 4 110kV and
Cancellation time: 24/06/2025 15:19
Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 127772
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202506241455_confirmed] Prices for interval 24-Jun-2025 14:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 14:55.
In accordance with Market Notice 127791 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506241515_confirmed] Prices for interval 24-Jun-2025 15:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 15:15.
In accordance with Market Notice 127802 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_confirmed] Prices for interval 24-Jun-2025 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 15:10.
In accordance with Market Notice 127799 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_confirmed] Prices for interval 24-Jun-2025 15:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 15:05.
In accordance with Market Notice 127797 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506241500_confirmed] Prices for interval 24-Jun-2025 15:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 15:00.
In accordance with Market Notice 127796 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202506241450_confirmed] Prices for interval 24-Jun-2025 14:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 24 June 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jun-2025 14:50.
In accordance with Market Notice 127788 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 24/06/2025 15:09
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-GH_RC12_250 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 127768
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 24/06/2025 15:09
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127769
Auto-generated on behalf of Manager NEM Real Time Operations