[EventId:202506160935_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 09:35
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 16 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0935 hrs on 16 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025
Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127572 is cancelled at 0715 hrs 16/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.
The Actual LOR1 condition is forecast to exist until 0730 hrs
The capacity reserve requirement is 700 MW
The minimum capacity reserve available is 638 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025
Cancellation of Actual (LOR1) condition in the QLD region - 14/06/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127542 is cancelled at 1808 hrs 14/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 724 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 12/06/2025
Cancellation of Actual (LOR1) condition in the QLD region - 12/06/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127513 is cancelled at 0725 hrs 12/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 12/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 12/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.
The Actual LOR1 condition is forecast to exist until 0730 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 715 MW
Manager NEM Real Time Operations
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the QLD Region on 11/06/2025
The Actual LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127504 is cancelled at 1945 hrs 11/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW
Manager NEM Real Time Operations