Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126487 is cancelled at 1910 hrs 10/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126467 is cancelled at 1540 hrs 10/04/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1577 MW.
Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
Refer to Market Notice 126464.
The cause of the unplanned outage of APD - Heywood - Mortlake 500 kV line in the VIC region has been identified and resolved. The outage has been completed and the APD - Heywood - Mortlake 500 kV line returned to service at 0948 hrs 10/04/2025
Constraint set(s) revoked: V-HYMO
Manager NEM Real Time Operations
Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
At 0825 hrs 10/04/2025 there was an unplanned outage of the APD - Heywood - Mortlake 500 kV line.
The following constraint set(s) invoked at 0835 hrs 10/04/2025
V-HYMO
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126458 is cancelled at 1845 hrs 09/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1549 MW
The minimum capacity reserve available is 1164 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/04/2025 to 1800 hrs 09/04/2025.
The forecast capacity reserve requirement is 1519 MW.
The minimum capacity reserve available is 1500 MW.
Manager NEM Real Time Operations