Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127557
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 15/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 15/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 16/06/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 15/06/2025
Direction - SA region 15/06/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 15/06/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 127551
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 15/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 15/06/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 15/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 12/06/2025
Cancellation - AEMO Intervention Event - SA region 12/06/2025
Refer to Market Notice 127518
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 15/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127535
Direction is cancelled from: 0400 hrs 15/06/2025
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 14 June 2025
NON-CONFORMANCE QLD1 Region Saturday, 14 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 14/06/2025 11:10 to 14/06/2025 12:05
Amount: 67 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127519
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 15/06/2025.
The direction update is issued at 1600 hrs 13/06/2025.
Manager NEM Real Time Operations
Initial - CHG0103468 - Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Change Start Date & Time: 19/06/2025 17:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:39
Outage End Date & Time: 19/06/2025 18:15:00
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Internal / Markets Portal Services
Identity Service may cause users to experience outages or few session issues for logins initated between 18:00 to 18:15 Market Time on 19/June/2025.
Internal / Market Portal Services will have an outage due to EMMS site transfer activities carried out in parallel, under a seperate change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.