Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 01/05/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
[EventId:202504301105_review] Prices for interval 30-Apr-2025 11:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 11:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504301100_review] Prices for interval 30-Apr-2025 11:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1055 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 11:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504301055_review] Prices for interval 30-Apr-2025 10:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1050 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504301050_review] Prices for interval 30-Apr-2025 10:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1045 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504301045_review] Prices for interval 30-Apr-2025 10:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202504301040_review] Prices for interval 30-Apr-2025 10:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 30 April 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Updated Victorian system normal voltage stability limit for the south-west Victoria
Refer to Market Notice 101368
AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.
The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.
Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 126779
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 29/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 30/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1830 hrs 30/04/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations