Market Notices

126589RECLASSIFY CONTINGENCY18/04/2025 05:29:41 AM

Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Cancellation time: 18/04/2025 05:29

Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 126588

Auto-generated on behalf of Manager NEM Real Time Operations
     
126588RECLASSIFY CONTINGENCY18/04/2025 04:24:40 AM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 18/04/2025 04:24 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
126587RECLASSIFY CONTINGENCY18/04/2025 03:29:40 AM

Cancellation of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Cancellation time: 18/04/2025 03:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 126586

Auto-generated on behalf of Manager NEM Real Time Operations
     
126586RECLASSIFY CONTINGENCY18/04/2025 02:27:20 AM

Reclassification of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Duration: 18/04/2025 02:27 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
126585RECLASSIFY CONTINGENCY17/04/2025 11:54:41 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 17/04/2025 23:54

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 126584

Auto-generated on behalf of Manager NEM Real Time Operations
     
126584RECLASSIFY CONTINGENCY17/04/2025 10:52:16 PM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 17/04/2025 22:52 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
126576PRICES UNCHANGED15/04/2025 02:40:19 PM

[EventId:202504151420_confirmed] Prices for interval 15-Apr-2025 14:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 15 April 2025

PRICES ARE NOW CONFIRMED for trading interval 15-Apr-2025 14:20.

In accordance with Market Notice 126566 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126575PRICES UNCHANGED15/04/2025 02:40:16 PM

[EventId:202504151440_confirmed] Prices for interval 15-Apr-2025 14:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 15 April 2025

PRICES ARE NOW CONFIRMED for trading interval 15-Apr-2025 14:40.

In accordance with Market Notice 126570 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126574PRICES UNCHANGED15/04/2025 02:40:17 PM

[EventId:202504151435_confirmed] Prices for interval 15-Apr-2025 14:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 15 April 2025

PRICES ARE NOW CONFIRMED for trading interval 15-Apr-2025 14:35.

In accordance with Market Notice 126569 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     