Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW
Manager NEM Real Time Operations
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Refer AEMO Electricity Market Notice 127501
In order to maintain the power system in a secure operating state in the NSW region, AEMO invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until 1810 hrs.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
A planned outage of Collector - Yass (3L) 330kV line in the NSW region was scheduled from 0700 hrs 10/06/2025 to 1500 hrs 16/06/2025.
The outage has been completed and Collector - Yass (3L) 330kV line returned to service at 1611 hrs 11/06/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025
At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.
The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 127439
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 127438
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 1150 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 0920 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations