NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025
NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025
Refer Market Notice 126468
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1520 hrs 10/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 11/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Release of PEC-1 and combined V-SA limits - 11 April 2025
Refer to market notice 123956
AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.
The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.
With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
NON-CONFORMANCE Region NSW1 Wednesday, 9 April 2025
NON-CONFORMANCE NSW1 Region Wednesday, 9 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 09/04/2025 19:00 to 09/04/2025 19:05
Amount: -38 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Refer Market Notice 126440
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1430 hrs 09/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 10/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
The foreseeable circumstance identified in Market Notice 126418 is cancelled.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 08/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations