NON-CONFORMANCE Region QLD1 Thursday, 5 June 2025
NON-CONFORMANCE QLD1 Region Thursday, 5 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 05/06/2025 19:30 to 05/06/2025 20:10
Amount: 23 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1800 hrs to 1830 hrs 12/06/2025.
The forecast capacity reserve requirement is 1618 MW.
The minimum capacity reserve available is 1595 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1730 hrs to 1830 hrs 10/06/2025.
The forecast capacity reserve requirement is 1502 MW.
The minimum capacity reserve available is 1301 MW.
AEMO Operations
Initial - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 05/06/2025 08:00:00
Change End Date & Time: 06/06/2025 17:00:00
Outage Start Date & Time: 05/06/2025 08:00:00
Outage End Date & Time: 05/06/2025 21:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127398 is cancelled at 1120 hrs 05/06/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127390 has been updated at 0520 hrs to the following:
[1.] From 1800 hrs 05/06/2025 to 1930 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 681 MW.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 04/06/2025 19:06
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 0
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1800 hrs 04/06/2025 to 1900 hrs 04/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 710 MW.
[2.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 716 MW.
Manager NEM Real Time Operations
Initial - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 05/06/2025 08:00:00
Change End Date & Time: 06/06/2025 17:00:00
Outage Start Date & Time: 05/06/2025 08:00:00
Outage End Date & Time: 05/06/2025 21:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.