127003RESERVE NOTICE12/05/2025 04:00:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 126998 has been updated at 1500 hrs 12/05/2025 to the following:

From 1430 hrs to 1500 hrs 15/05/2025.
The forecast capacity reserve requirement is 461 MW.
The minimum capacity reserve available is 453 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126999MARKET INTERVENTION12/05/2025 03:15:09 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126997

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0930 hrs 13/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 12/05/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126998RESERVE NOTICE12/05/2025 02:03:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126997MARKET INTERVENTION12/05/2025 12:40:52 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 13/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126985MARKET INTERVENTION11/05/2025 03:59:44 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025

Refer Market Notice 126981

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1600 hrs 11/05/2025.

Manager NEM Real Time Operations
     
126984MARKET INTERVENTION11/05/2025 03:27:46 PM

Cancellation - AEMO Intervention Event - SA region 10/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 10/05/2025

Refer to Market Notice 126977

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 11/05/2025.


Manager NEM Real Time Operations
     
126983MARKET INTERVENTION11/05/2025 03:27:24 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126978

Direction is cancelled from: 1530 hrs 11/05/2025

Manager NEM Real Time Operations
     
126982MARKET INTERVENTION11/05/2025 02:55:32 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 126979

Direction is cancelled from: 1500 hrs 11/05/2025

Manager NEM Real Time Operations
     
126981MARKET INTERVENTION11/05/2025 12:44:59 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 12/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     