Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
Refer AEMO Electricity Market Notice 127501
In order to maintain the power system in a secure operating state in the NSW region, AEMO invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until 1810 hrs.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 11/06/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_575BC182 from 1755 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
A planned outage of Collector - Yass (3L) 330kV line in the NSW region was scheduled from 0700 hrs 10/06/2025 to 1500 hrs 16/06/2025.
The outage has been completed and Collector - Yass (3L) 330kV line returned to service at 1611 hrs 11/06/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025
At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.
The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127419
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127418
Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127450 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked:
I-VS_250
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
AEMO has taken the following action to maintain power system security at 1250 hrs 07/06/2025.
Constraint set invoked:
I-VS_250
Duration: 1255 hrs until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 127439
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.
Manager NEM Real Time Operations