Non-credible contingency event - QLD region - 11/06/2025
Non-credible contingency event - QLD region - 11/06/2025
At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
Inter-regional transfer limit variation - Collector - Yass (3L) 330kV line - NSW region - 11/06/2025
A planned outage of Collector - Yass (3L) 330kV line in the NSW region was scheduled from 0700 hrs 10/06/2025 to 1500 hrs 16/06/2025.
The outage has been completed and Collector - Yass (3L) 330kV line returned to service at 1611 hrs 11/06/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025
At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.
The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 127439
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 127438
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 1150 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 0920 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/06/2025
Non-credible contingency event - VIC region - 06/06/2025
At 0830 hrs the Wodonga No 2 330kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.
The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC
and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC
These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations