Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Refer to Market Notice 127682
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127792
Direction is cancelled from: 1400 hrs 25/06/2025
Manager NEM Real Time Operations
Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241500_review] Prices for interval 24-Jun-2025 15:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1455 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127740
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.
The direction update is issued at 1600 hrs 24/06/2025.
Manager NEM Real Time Operations
[EventId:202506241455_review] Prices for interval 24-Jun-2025 14:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 14:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.