Initial - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 05/06/2025 08:00:00
Change End Date & Time: 06/06/2025 17:00:00
Outage Start Date & Time: 05/06/2025 08:00:00
Outage End Date & Time: 05/06/2025 21:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127382 has been updated at 1600 hrs to the following:
[1.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 705 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 04/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127381 is cancelled at 1416 hrs 04/06/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1730 hrs 04/06/2025 to 1900 hrs 04/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 709 MW.
[2.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 682 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 05/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0800 hrs 05/06/2025 to 0830 hrs 05/06/2025.
The forecast capacity reserve requirement is 1172 MW.
The minimum capacity reserve available is 902 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 04/06/2025 to 1900 hrs 04/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 721 MW.
Manager NEM Real Time Operations
CHG0103386 | Production | Renewal and update of AEMO's FBS-Prod-Hub.aemo.com.au server certificate
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to "FBS-Prod-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Prod-Hub.aemo.com.au
apis.prod.aemo.com.au
hub.aemo.com.au
prod.frchub.net
apis.prod.marketnet.net.au
hub.marketnet.net.au
Participants WILL need to update the profile that communicates with the above domains. This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below: https://www.digicert.com/secure/download-certificate/0zb6n7hdvs5c84j41twxz695ft63p2m
Change duration will be as below.
Start - 22/06/2025 10:00:00 AM AEST
End - 22/06/2025 14:00:00 PM AEST
NON-CONFORMANCE Region QLD1 Tuesday, 3 June 2025
NON-CONFORMANCE QLD1 Region Tuesday, 3 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 03/06/2025 15:00 to 03/06/2025 15:05
Amount: -33 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 05/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:
From 0730 hrs to 0800 hrs 05/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1129 MW.
AEMO Operations