Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127740
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.
The direction update is issued at 1600 hrs 24/06/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 24 June 2025
NON-CONFORMANCE VIC1 Region Tuesday, 24 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 24/06/2025 13:00 to 24/06/2025 13:30
Amount: 15 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Direction - NSW region - 23/06/2025
Cancellation - Direction - NSW region - 23/06/2025
Refer to Market Notice 127745.
The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.
Manager NEM Real Time Operations
Direction - NSW region 23/06/2025
Direction - NSW region 23/06/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.
A further market notice will be issued when all directions related to this requirement have been cancelled.
For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127696
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/06/2025.
The direction update is issued at 1500 hrs 23/06/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 22 June 2025
NON-CONFORMANCE NSW1 Region Sunday, 22 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW02
Duration: 22/06/2025 21:55 to 22/06/2025 22:10
Amount: -39 MW
Constraint: NC-N_BW02
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127683
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/06/2025.
The direction update is issued at 1500 hrs 22/06/2025.
Manager NEM Real Time Operations