Market Notices

127835MARKET SYSTEMS25/06/2025 09:48:25 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025

Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127833NON-CONFORMANCE25/06/2025 06:10:17 AM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127780NON-CONFORMANCE24/06/2025 01:30:16 PM

NON-CONFORMANCE Region VIC1 Tuesday, 24 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 24 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 24/06/2025 13:00 to 24/06/2025 13:30
Amount: 15 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127778MARKET SYSTEMS24/06/2025 10:52:42 AM

Completed - CHG0103783 - Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0103783

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127743INTER-REGIONAL TRANSFER23/06/2025 05:44:44 PM

Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025

At 1719 hrs 23/06/2025 there was an unplanned outage of Darlington Point - Wagga No.63 330 kV line. The Darlington Point - Balranald No. X5 220 kV line consequently tripped due to a control scheme for the trip of the above line as per design.

The following constraint set(s) invoked at 1725 hrs 23/06/2025
N-DPWG_63_X5

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127699MARKET SYSTEMS23/06/2025 11:02:20 AM

Initial - CHG0103783 - Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0103783

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 23/06/2025 07:00:15
Change End Date & Time: 23/06/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 23rd of June 2025, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Sydney.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Sydney as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Brisbane will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Sydney, to switch these connections to the Brisbane site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Brisbane site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127698MARKET SYSTEMS23/06/2025 10:59:30 AM

Completed - CHG0103386 - Renewal and update of AEMO's FBS-Prod-Hub.aemo.com.au server certificate.

Change Number: CHG0103386

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MarketNet
Change Title: Renewal and update of AEMO's FBS-Prod-Hub.aemo.com.au server certificate.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127697NON-CONFORMANCE22/06/2025 10:10:23 PM

NON-CONFORMANCE Region NSW1 Sunday, 22 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 22 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 22/06/2025 21:55 to 22/06/2025 22:10
Amount: -39 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
127677NON-CONFORMANCE21/06/2025 09:50:11 AM

NON-CONFORMANCE Region QLD1 Saturday, 21 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 21 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/06/2025 09:10 to 21/06/2025 09:50
Amount: 27 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     