127372MARKET INTERVENTION04/06/2025 10:16:11 AM

Direction - SA region 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 04/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1035 hrs on 04/06/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
127371MARKET INTERVENTION04/06/2025 10:16:04 AM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 127370


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1015 hrs 04/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1030 hrs 04/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1230 hrs 04/06/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
127370MARKET INTERVENTION04/06/2025 09:58:14 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 127369

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 04/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1015 hrs 04/06/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
127369MARKET INTERVENTION04/06/2025 09:48:04 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 05/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127324INTER-REGIONAL TRANSFER28/05/2025 05:55:45 PM

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.

The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC

and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC

These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127306MARKET INTERVENTION27/05/2025 01:55:06 PM

Cancellation - AEMO Intervention Event - SA region 22/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/05/2025

Refer to Market Notice 127159

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.


Manager NEM Real Time Operations
     
127305MARKET INTERVENTION27/05/2025 01:54:36 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127276

Direction is cancelled from: 1400 hrs 27/05/2025

Manager NEM Real Time Operations
     
127301INTER-REGIONAL TRANSFER27/05/2025 03:50:02 AM

Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025

At 0337 hrs 27/05/2025 there was an unplanned outage of Brinkworth - Templers West 275 kV line.

The following constraint set(s) invoked at 0340 hrs 27/05/2025
S-BRTW

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127276MARKET INTERVENTION26/05/2025 03:59:20 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127232

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.

The direction update is issued at 1600 hrs 26/05/2025.

Manager NEM Real Time Operations
     