Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127389
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 7/06/2025.
The direction update is issued at 1600 hrs 5/06/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1800 hrs to 1830 hrs 12/06/2025.
The forecast capacity reserve requirement is 1618 MW.
The minimum capacity reserve available is 1595 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1730 hrs to 1830 hrs 10/06/2025.
The forecast capacity reserve requirement is 1502 MW.
The minimum capacity reserve available is 1301 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127398 is cancelled at 1120 hrs 05/06/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127390 has been updated at 0520 hrs to the following:
[1.] From 1800 hrs 05/06/2025 to 1930 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 681 MW.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 04/06/2025 19:06
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 0
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1800 hrs 04/06/2025 to 1900 hrs 04/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 710 MW.
[2.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 716 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127382 has been updated at 1600 hrs to the following:
[1.] From 1800 hrs 05/06/2025 to 1900 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 705 MW.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127387
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 05/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 05/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 06/06/2025 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations