Cancellation - AEMO Intervention Event - SA region 12/07/2025
Cancellation - AEMO Intervention Event - SA region 12/07/2025
Refer to Market Notice 128101
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 13/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128102
Direction is cancelled from: 1600 hrs 13/07/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 128097
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 12/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1450 hrs 12/07/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1450 hrs 12/07/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2200 hrs 12/07/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 13/07/2025 .
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 12/07/2025
Direction - SA region 12/07/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1455hrs on 12/07/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 11/07/2025
Cancellation - AEMO Intervention Event - SA region 11/07/2025
Refer to Market Notice 128093
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 12/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128094
Direction is cancelled from: 1600 hrs 12/07/2025
Manager NEM Real Time Operations