Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113424 is cancelled at 1815 hrs 18/01/2024.
Manager NEM Real Time Operations
[EventId:202401181600_review] Prices for interval 18-Jan-2024 16:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1555 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 16:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401181555_review] Prices for interval 18-Jan-2024 15:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 15:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401181550_review] Prices for interval 18-Jan-2024 15:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 15:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 952 MW
The minimum capacity reserve available is 857 MW
Manager NEM Real Time Operations
[EventId:202401181545_review] Prices for interval 18-Jan-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401181540_review] Prices for interval 18-Jan-2024 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401181535_review] Prices for interval 18-Jan-2024 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 18 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Jan-2024 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1800 hrs 25/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1418 MW.
AEMO Operations