Filter by category
Filter by Date
Notice type *
MARKET SUSPENSION
Notice type description *
Market suspended in region(s).
External reference *
Declaration of electricity market suspension
Reason *
AEMO ELECTRICITY MARKET NOTICE
Declaration of electricity market suspension
AEMO declares the spot market suspended in the NEM with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1400 hrs on 05 September 2024 until further notice. Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
There has been a failure of the NEM dispatch process, and all participants to follow existing targets until further notice.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2023
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117203 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117202 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117201 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
NON-CONFORMANCE Region QLD1 Thursday, 27 June 2024
NON-CONFORMANCE QLD1 Region Thursday, 27 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 27/06/2024 12:40 to 27/06/2024 13:00
Amount: -45 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 532 MW.
The minimum capacity reserve available is 505 MW.
2. From 1730 hrs to 2030 hrs 03/07/2024.
The forecast capacity reserve requirement is 526 MW.
The minimum capacity reserve available is 496 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 02/07/2024.
The forecast capacity reserve requirement is 536 MW.
The minimum capacity reserve available is 454 MW.
2. From 1730 hrs to 2130 hrs 02/07/2024.
The forecast capacity reserve requirement is 546 MW.
The minimum capacity reserve available is 414 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 2130 hrs 01/07/2024.
The forecast capacity reserve requirement is 514 MW.
The minimum capacity reserve available is 467 MW.
AEMO Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 25 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 25/06/2024 09:35 to 25/06/2024 09:50
Amount: -40 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 24/06/2024 18:30 to 24/06/2024 20:20
Amount: 49 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations