Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 127442
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 07/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 07/06/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/06/2025
Cancellation - AEMO Intervention Event - SA region 06/06/2025
Refer to Market Notice 127412
The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 07/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127440
Direction is cancelled from: 1630 hrs 07/06/2025
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 07/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127413
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 07/06/2025.
The direction update is issued at 0915 hrs 07/06/2025.
Manager NEM Real Time Operations
Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Correction to Market Notice 127432
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1915 hrs 06/06/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1815 hrs 06/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1694 MW
The minimum capacity reserve available is 1692 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 06/06/2025 to 1800 hrs 06/06/2025.
The forecast capacity reserve requirement is 1598 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations