114059NON-CONFORMANCE31/01/2024 09:45:16 AM

NON-CONFORMANCE Region QLD1 Wednesday, 31 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 31 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 31/01/2024 09:35 to 31/01/2024 09:45
Amount: 40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
114056MARKET SYSTEMS31/01/2024 08:43:18 AM

CHG0082222 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0082222

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System

Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
114025MARKET INTERVENTION30/01/2024 04:02:58 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114012MARKET SYSTEMS30/01/2024 01:47:21 PM

CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Pre-Production MSATS r50.0.5 Patch Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
113983NON-CONFORMANCE29/01/2024 04:05:13 PM

NON-CONFORMANCE Region NSW1 Monday, 29 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
113972MARKET INTERVENTION29/01/2024 04:18:46 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113958RESERVE NOTICE29/01/2024 09:17:19 AM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:

1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.

2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.

AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.

AEMO Operations
113954NON-CONFORMANCE28/01/2024 10:05:15 PM

NON-CONFORMANCE Region SA1 Sunday, 28 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 28 January 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 28/01/2024 21:55 to 28/01/2024 22:05
Amount: 38 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
113930MARKET INTERVENTION28/01/2024 04:59:36 PM

Direction - SA region 28/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 28/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 28/01/2024.

Intervention pricing does not apply to this AEMO intervention event.