114693MARKET INTERVENTION14/02/2024 06:09:02 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 13/02/2024

Refer Market Notice 114656

The AEMO Intervention Event and all associated directions are cancelled from 0610 hrs 14/02/2024

Manager NEM Real Time Operations
114688INTER-REGIONAL TRANSFER14/02/2024 03:05:05 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0235 hrs 14/02/2024

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for return to service details

Manager NEM Real Time Operations
114687INTER-REGIONAL TRANSFER14/02/2024 01:30:25 AM

Inter-regional transfer limit variation: South Morang - Sydenham No 1 and 2 500 kV lines (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The South Morang - Sydenham No 1 and 2 500 kV lines have been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0105 hrs 14/02/2024

V-SMSY

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details

Manager NEM Real Time Operations
114686INTER-REGIONAL TRANSFER14/02/2024 01:24:53 AM

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - VIC region - 13/02/2024 -

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - 13/02/2024

At 1308 hrs 13/02/2024 the Moorabool - Sydenham No1 and No2 500 kV lines tripped.

Refer Market notices 114577 and 114625.

The following constraint set(s) are invoked :

V-X_MLSY
F-V-X_ML_BUSTIE_500
I-VS_050

These constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer to the Network outage scheduler (NOS) for more details:

Manager NEM Real Time Operations
114658MARKET INTERVENTION13/02/2024 05:31:26 PM

Update - Direction - SA Region - 12/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 12/02/2024

Refer Market Notice 114536

The AEMO intervention event that commenced from interval ending 1705 hrs on 12/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114656MARKET INTERVENTION13/02/2024 05:38:24 PM

Direction - VIC region 13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - VIC region 13/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the VIC region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1735 hrs on 13/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
114648MARKET INTERVENTION13/02/2024 05:21:13 PM

Possible intervention to manage power system security in VIC region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in VIC region

The synchronous generating units currently expected to be synchronised in VIC from 1830 hrs 13/02/2024 will be inadequate to maintain a secure operating state in VIC .

AEMO estimates that, in the absence of sufficient market response by 1730 hrs 13/02/2024, AEMO may need to intervene by issuing a direction requiring one or more VIC synchronous generating unit(s) to operate or remain synchronised to maintain power system security in VIC.

Manager NEM Real Time Operations
114603MARKET INTERVENTION13/02/2024 02:18:14 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
114602MARKET INTERVENTION13/02/2024 02:18:13 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations