115408INTER-REGIONAL TRANSFER01/03/2024 08:15:32 AM

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.

Constraint set(s) invoked: N-MPTX

The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115403MARKET INTERVENTION01/03/2024 12:21:07 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 02/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115398INTER-REGIONAL TRANSFER29/02/2024 07:06:55 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_54F2D1C0 from 1850 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
115394RESERVE NOTICE29/02/2024 07:00:09 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115374 is cancelled at 1900 hrs 29/02/2024.

Manager NEM Real Time Operations
115374RESERVE NOTICE29/02/2024 04:26:50 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1001 MW.

Manager NEM Real Time Operations
115372INTER-REGIONAL TRANSFER29/02/2024 04:18:08 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA-BRIS_54F2ABFD_1 from 1610 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
115371RESERVE NOTICE29/02/2024 03:49:22 PM

Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115370 is cancelled at 1545 hrs 29/02/2024.

Manager NEM Real Time Operations
115370RESERVE NOTICE29/02/2024 03:12:55 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1500 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1066 MW

Manager NEM Real Time Operations
115364MARKET INTERVENTION29/02/2024 04:46:21 PM

Direction - SA region 29/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 29/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 29/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations