Market Notices

114197MARKET INTERVENTION03/02/2024 01:32:47 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/02/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114196MARKET INTERVENTION03/02/2024 01:31:47 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 04/02/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 03/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114184NON-CONFORMANCE03/02/2024 02:45:15 AM

NON-CONFORMANCE Region QLD1 Saturday, 3 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 3 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 03/02/2024 02:25 to 03/02/2024 02:45
Amount: -36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114166MARKET INTERVENTION02/02/2024 05:01:04 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114148GENERAL NOTICE02/02/2024 10:30:00 AM

NEM Local Temperature Alerts for NSW, SA, VIC from 02 Feb 2024 to 06 Feb 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Mudgee Ap (39+ Deg C): 4th Feb
Yass (39+ Deg C): 4th Feb

SA
Clare High School (39+ Deg C): 4th Feb
Port Augusta Ap (39+ Deg C): 3rd Feb, 4th Feb

VIC
Mildura Ap (39+ Deg C): 4th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
114136NON-CONFORMANCE01/02/2024 10:05:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 21:40 to 01/02/2024 22:05
Amount: -24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114131NON-CONFORMANCE01/02/2024 06:40:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 18:30 to 01/02/2024 18:40
Amount: 50 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114122MARKET INTERVENTION01/02/2024 04:00:09 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114114NON-CONFORMANCE01/02/2024 01:45:21 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm