Market Notices

Notice type *
MARKET SUSPENSION

Notice type description *
Market suspended in region(s).

External reference *
Declaration of electricity market suspension

Reason *
AEMO ELECTRICITY MARKET NOTICE

Declaration of electricity market suspension

AEMO declares the spot market suspended in the NEM with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1555 hrs on 05 September 2024 until further notice. Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.

Manager NEM Real Time Operations

117302NON-CONFORMANCE06/07/2024 01:55:24 PM

NON-CONFORMANCE Region SA1 Saturday, 6 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 6 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BOWWPV1
Duration: 06/07/2024 13:20 to 06/07/2024 13:55
Amount: 6 MW
Constraint: NC-S_BOWWPV1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117299NON-CONFORMANCE06/07/2024 04:30:14 AM

NON-CONFORMANCE Region QLD1 Saturday, 6 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 6 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 06/07/2024 04:00 to 06/07/2024 04:30
Amount: 33 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117287NON-CONFORMANCE03/07/2024 10:00:13 PM

NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CALL_B_1
Duration: 03/07/2024 21:55 to 03/07/2024 22:00
Amount: -97 MW
Constraint: NC-Q_CALL_B_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117282RESERVE NOTICE03/07/2024 05:16:36 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 03/07/2024 to 1930 hrs 03/07/2024.
The forecast capacity reserve requirement is 1490 MW.
The minimum capacity reserve available is 1179 MW.

Manager NEM Real Time Operations
     
117279NON-CONFORMANCE03/07/2024 02:50:15 PM

NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-1
Duration: 03/07/2024 14:40 to 03/07/2024 14:50
Amount: -18 MW
Constraint: NC-Q_STAN-1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117277RESERVE NOTICE03/07/2024 07:15:13 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117276 is cancelled at 0715 hrs 03/07/2024.

Manager NEM Real Time Operations
     
117276RESERVE NOTICE03/07/2024 04:44:19 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 3/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No.117274 has been updated at 0445 hrs to the following:

[1.] From 0800 hrs 03/07/2024 to 0830 hrs 03/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 621 MW.

Manager NEM Real Time Operations
     
117275NON-CONFORMANCE02/07/2024 06:40:17 PM

NON-CONFORMANCE Region NSW1 Tuesday, 2 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 2 July 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: BHBG1, BHBL1
Aggregate Dispatch Group: BHBESS_ADG1
Duration: 02/07/2024 18:30 to 02/07/2024 18:40
Amount: -10 MW
Constraint: NC-N_BHBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117274RESERVE NOTICE02/07/2024 05:35:25 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 3/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No.117273 has been updated at 1709 hrs to the following:

[1.] From 0800 hrs 03/07/2024 to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 590 MW.


Manager NEM Real Time Operations
     