Market Notices

54474RESERVE NOTICE13/07/2016 01:30:17 PM

Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 14 July 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 14 July 2016

AEMO declares a Forecast LOR1 condition for the SA Region.

From 1730 hrs to 1830 hrs 14 July 2016

The contingency capacity reserve required is 400 MW

The minimum reserve available is 221 MW


Manager NEM Real Time Operations
54470MARKET SYSTEMS13/07/2016 05:29:47 PM

CHG0039818: Planned System Outage to the Energy Forecasting Web Portal

Change Number: CHG0039818

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Energy Forecasting Web Portal

Change Title: Planned System Outage to the Energy Forecasting Web Portal

Change Start Date & Time: 15/07/2016 09:00:00 AEST

Change End Date & Time: 15/07/2016 13:00:00 AEST

Outage Start Date & Time: 15/07/2016 09:00:00 AEST

Outage End Date & Time: 15/07/2016 12:00:00 AEST


Change Description:

Update of Forecasting Interactive Website (http://forecasting.aemo.com.au) with usability enhancements and support for previous years forecasts.

Environment: Production

Participant Impact and Requirements:

Forecasting Interactive Website and associated Administration Webpage may not be available during the deployment window. Users need to try accessing the website after the deployment is completed as mentioned in the timeline.

Support Information:

Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54469MARKET SYSTEMS13/07/2016 05:29:03 PM

CHG0039787: Planned System Outage - Gas Supply Hub Pre-production

Change Number: CHG0039787

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: Planned System Outage - Gas Supply Hub Pre-production

Change Start Date & Time: 14/07/2016 10:00:00 AEST

Change End Date & Time: 14/07/2016 14:00:00 AEST

Outage Start Date & Time: 14/07/2016 10:00:00 AEST

Outage End Date & Time: 14/07/2016 14:00:00 AEST


Change Description:

Maintenance is performed on Gas Supply Hub periodically to improve security, reliability and performance.

Environment: Pre-Production

Participant Impact and Requirements:

All access to the Preproduction Gas Supply Hub (Exchange Trading System) will be unavailable during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54451RESERVE NOTICE12/07/2016 04:31:49 PM

Update - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 13 July 2016

AEMO ELECTRICITY MARKET NOTICE

Update Forecast Lack of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 13 July 2016

See MN - 54449

AEMO declares the Forecast LOR1 condition for the SA Region.

From 1800 hrs to 2100 hrs 13 July 2016

The contingency capacity reserve required is 400 MW

The minimum reserve available is 225 MW

Manager NEM Real Time Operations
54449RESERVE NOTICE12/07/2016 03:50:09 PM

Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 12 July 2016 and 13 July 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 12 July 2016 and 13 July 2016

AEMO declares a Forecast LOR1 condition for the SA Region.

From 1800 hrs to 1900 hrs 12 July 2016 and
From 1830 hrs to 1900 hrs 13 July 2016

The contingency capacity reserve required is 400 MW

The minimum reserve available is 312 MW


Manager NEM Real Time Operations
54440RESERVE NOTICE12/07/2016 03:03:13 PM

Update of the Forecast Lack Of Reserve Level 1 (LOR1) condition in the South Australia region - STPASA - 15/07/2016

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the South Australia region advised in AEMO Electricity Market Notice No. 54397 has been updated at 1400hrs 12/07/2016 to the following:

From 15/07/2016 1800 hrs to 2030 hrs
The contingency capacity reserve required is 400 MW
The minimum reserve available is 290 MW

Ashley Dunn
Operations Planning
54435RESERVE NOTICE12/07/2016 01:00:00 PM

Forecast Lack of Reserve Level 1 (LOR1) in the xx Region - PDPASA - 13 July 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Lack of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 13 July 2016

AEMO declares a Forecast LOR1 condition for the SA Region.

From 1800 hrs to 1830 hrs 13 July 2016

The contingency capacity reserve required is 400 MW

The minimum reserve available is 313 MW


Manager NEM Real Time Operations
54397RESERVE NOTICE11/07/2016 03:17:48 PM

Update of the Forecast Lack Of Reserve Level 1 (LOR1) condition in the South Australia region - STPASA - 14/07/2016

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the South Australia region advised in AEMO Electricity Market Notice No. 54390 has been updated at 1400 hrs 11/07/2016 to the following:

From 14/07/2016 1800 hrs to 2130 hrs
The contingency capacity reserve required is 400 MW
The minimum reserve available is 230 MW

Ashley Dunn
Operations Planning
54390RESERVE NOTICE10/07/2016 02:20:35 PM

Update - FORECAST LACK OF RESERVE LEVEL 1 (LOR1) in the South Australia region (ST PASA).


AEMO ELECTRICITY MARKET NOTICE

Update - FORECAST LACK OF RESERVE LEVEL 1 (LOR1) in the South Australia region (ST PASA).

Refer Electricity Market Notice 54386

AEMO declares a forecast LOR1 condition for the South Australia region for the following period.

Thursday 14th July 2016 from 1800 hrs to 2100 hrs

The contingency capacity reserve required is 400 MW

The minimum reserve available is 303 MW

Manager NEM Real Time Operations