Market Notices

127371MARKET INTERVENTION04/06/2025 10:16:04 AM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 127370


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1015 hrs 04/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1030 hrs 04/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1230 hrs 04/06/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
127370MARKET INTERVENTION04/06/2025 09:58:14 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 127369

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 04/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1015 hrs 04/06/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
127369MARKET INTERVENTION04/06/2025 09:48:04 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 05/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127306MARKET INTERVENTION27/05/2025 01:55:06 PM

Cancellation - AEMO Intervention Event - SA region 22/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/05/2025

Refer to Market Notice 127159

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.


Manager NEM Real Time Operations
     
127305MARKET INTERVENTION27/05/2025 01:54:36 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127276

Direction is cancelled from: 1400 hrs 27/05/2025

Manager NEM Real Time Operations
     
127304POWER SYSTEM EVENTS27/05/2025 12:30:40 PM

Update - Non-credible contingency event - NSW region - 07/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 07/03/2025

Refer AEMO Electricity Market Notice 125536

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will no longer reclassify this event as a credible contingency event.

Region: NSW

Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line

Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025

Constraint set(s) invoked: NONE

Manager NEM Real Time Operations
     
127276MARKET INTERVENTION26/05/2025 03:59:20 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127232

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.

The direction update is issued at 1600 hrs 26/05/2025.

Manager NEM Real Time Operations
     
127232MARKET INTERVENTION25/05/2025 03:58:25 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127193

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/05/2025.

The direction update is issued at 1600 hrs 25/05/2025.

Manager NEM Real Time Operations
     
127193MARKET INTERVENTION24/05/2025 03:42:33 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127165

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/05/2025.

The direction update is issued at 1540 hrs 24/05/2025.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm