112251RESERVE NOTICE13/12/2023 02:45:53 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1530 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1315 MW.


AEMO Operations
112243RESERVE NOTICE13/12/2023 01:03:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1700 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1286 MW.
The minimum capacity reserve available is 988 MW.


Manager NEM Real Time Operations
112242RESERVE NOTICE13/12/2023 12:58:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1930 hrs 14/12/2023 to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1323 MW.


Manager NEM Real Time Operations
112209RESERVE NOTICE12/12/2023 03:04:17 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 112182 has been updated at 1400 hrs 12/12/2023 to the following:

From 1730 hrs to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1193 MW.


AEMO Operations
112208RESERVE NOTICE12/12/2023 03:05:35 PM

STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112183 has been updated at 1400 hrs 12/12/2023 to the following:

From 2000 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1569 MW.


AEMO Operations
112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112188INTER-REGIONAL TRANSFER11/12/2023 04:31:45 PM

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

At 1446 hrs 11/12/2023 there was an unplanned outage of Blyth West- Munno Para 275 kV Line.

However, due to the concurrent Non-credible contingency event - SA region - 11/12/2023, refer AEMO Electricity Market Notice 112187, additional inter-regional constraints were not required until the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) invoked at 1610 hrs 11/12/2023
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112183RESERVE NOTICE11/12/2023 03:13:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:

From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.