Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127407
Direction is cancelled from: 1600 hrs 06/06/2025
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1900 hrs 06/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 06/06/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127403
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 06/06/2025.
The direction update is issued at 1445 hrs 06/06/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127389
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 7/06/2025.
The direction update is issued at 1600 hrs 5/06/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025
Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127394 is cancelled at 1945 hrs 04/06/2025.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 04/06/2025 19:06
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 0
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025
Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127393 is cancelled at 1845 hrs 04/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 682 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1540 MW
The minimum capacity reserve available is 1540 MW
Manager NEM Real Time Operations