Market Notices

126499MARKET INTERVENTION11/04/2025 03:57:59 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126501


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 11/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0100 hrs 12/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 12/04/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
126498MARKET INTERVENTION11/04/2025 02:48:27 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126495

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 12/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 11/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126495MARKET INTERVENTION11/04/2025 12:10:51 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 12/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126471MARKET INTERVENTION10/04/2025 03:21:04 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025

Refer Market Notice 126468

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1520 hrs 10/04/2025.

Manager NEM Real Time Operations
     
126468MARKET INTERVENTION10/04/2025 01:01:05 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 11/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126465INTER-REGIONAL TRANSFER10/04/2025 10:00:31 AM

Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

Refer to Market Notice 126464.

The cause of the unplanned outage of APD - Heywood - Mortlake 500 kV line in the VIC region has been identified and resolved. The outage has been completed and the APD - Heywood - Mortlake 500 kV line returned to service at 0948 hrs 10/04/2025

Constraint set(s) revoked: V-HYMO

Manager NEM Real Time Operations
     
126464INTER-REGIONAL TRANSFER10/04/2025 08:49:30 AM

Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

At 0825 hrs 10/04/2025 there was an unplanned outage of the APD - Heywood - Mortlake 500 kV line.

The following constraint set(s) invoked at 0835 hrs 10/04/2025
V-HYMO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126442MARKET INTERVENTION09/04/2025 02:42:04 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025

Refer Market Notice 126440

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1430 hrs 09/04/2025.

Manager NEM Real Time Operations
     
126440MARKET INTERVENTION09/04/2025 01:04:53 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 10/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     