AEMO ELECTRICITY MARKET NOTICE

Declaration of electricity market suspension

AEMO declares the spot market suspended in the NEM with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1400 hrs on 05 September 2024 until further notice. Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.

There has been a failure of the NEM dispatch process, and all participants to follow existing targets until further notice.

Manager NEM Real Time Operations

117737GENERAL NOTICE21/08/2024 10:37:27 AM

Planned outage of Kerang - Wemen 220 kV line in the VIC region on 23/08/2024.

AEMO ELECTRICITY MARKET NOTICE

The Kerang - Wemen 220 kV line in the Victorian (VIC) region is planned to be out of service from 0600 hrs to 1800 hrs on 23/08/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
117728MARKET SYSTEMS20/08/2024 03:15:50 PM

CHG0095840 | Production | AEMO will be undertaking maintenance activities on the DWGM system

Change Number: CHG0095840

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the DWGM system

Change Start Date & Time: 20/08/2024 18:30:35 AEST
Change End Date & Time: 21/08/2024 01:30:35 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117726MARKET SYSTEMS20/08/2024 09:37:40 AM

CHG0091298 | Completed | Production | Change to MarketNet SSL VPN

Change Number: CHG0091298

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Market Network

Change Title: Change to MarketNet SSL VPN

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117705MARKET SYSTEMS16/08/2024 05:04:55 PM

CHG0093465 | Production | AEMO will be undertaking maintenance activities on the STTM system.

Change Number: CHG0093465

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the STTM system.

Change Start Date & Time: 20/08/2024 18:31:12 AEST

Change End Date & Time: 21/08/2024 08:31:12 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the STTM system. Whilst no outage is expected there is potential for transient performance degradation during the change.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




     
117704MARKET SYSTEMS16/08/2024 04:56:17 PM

CHG0095739 | Production | AEMO will be undertaking maintenance activities on the system.

Change Number: CHG0095739

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the system.

Change Start Date & Time: 20/08/2024 13:00:19 AEST

Change End Date & Time: 20/08/2024 16:00:19 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system. Whilst no outage is expected there is potential for transient performance degradation during the change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117703MARKET SYSTEMS16/08/2024 04:53:51 PM

CHG0087952 | Completed | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)

Change Number: CHG0087952

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Retail Pre-Production Data refresh (CATS and EMDM)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
117696MARKET SYSTEMS16/08/2024 01:46:11 PM

CHG0095132 | Cancelled | Production | AEMO will be undertaking maintenance activities on the DWGM system

Change Number: CHG0095132

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal
Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
117694GENERAL NOTICE16/08/2024 10:44:53 AM

Network Augmentation Commissioned - NSW Region - 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 16/08/2024

Commissioned: Munmorah - Waratah S BESS 2Y 330 kV Line

Manager NEM Real Time Operations
     
117693MARKET SYSTEMS16/08/2024 08:40:42 AM

CHG0091534 | Completed | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0091534

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm