Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024
Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.114929 is cancelled at 1945 hrs 21/02/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Refer AEMO Electricity Market Notice 114927
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 428 MW
The minimum capacity reserve available is 277 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 431 MW
The minimum capacity reserve available is 414 MW
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Directlink DC2 - NSW region - 19/02/2024
Inter-regional transfer limit variation - Directlink DC2 - NSW region - 19/02/2024
A planned outage of Directlink DC2 in the NSW region was scheduled from 2000 hrs 16/02/2024 to 1701 hrs 20/02/2024.
The outage has been completed and Directlink DC2 returned to service at 1425 hrs 19/02/2024.
The following constraint set(s) revoked at 1425 hrs 19/02/2024
N-MBTE_1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0083624 | Completed | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082609 | Completed | Production | MSATS-CATS Production Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Short Notice Outage - Directlink - NSW Region - 16 February 2024
Short Notice Outage - Directlink - NSW Region - 16 February 2024
A short notice outage of Directlink cable DC2 in the NSW Region.
Constraint set N-MBTE_1 invoked from 2010 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all three legs of Directlink .
The following constraint set was invoked at 1440 hrs 16/02/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Moorabool Sydenham 500 kV lines - Vic region - 15/02/2024
At 1905 hrs 15/02/2024 in the Victoria region interim work was completed at Moorabool and Sydenham terminal stations to provide additional 500 kV bus ties.
As a result of this completed work the South Australia region is no longer on a credible risk of separation.
Constraint set changes.
Invoked:
V-X_MLSY_MLTS_TIE
Revoked:
F-V-X_ML_BUSTIE_500
I-VS_050
S-X_BC_CP
V-X_MLSY
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Rfer Market Notices 114577, 114768, 114686
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations