Market Notices

126702MARKET INTERVENTION23/04/2025 04:00:19 PM

Direction - SA region 23/04/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 23/04/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 23/04/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
126695MARKET INTERVENTION23/04/2025 02:40:45 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126691

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 24/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 23/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126694MARKET INTERVENTION23/04/2025 05:16:08 PM

Cancellation - AEMO Intervention Event - SA region 18/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 18/04/2025

Refer to Market Notice 126592

The AEMO Intervention Event and all associated directions are cancelled from 1715 hrs on 23/04/2025.


Manager NEM Real Time Operations
     
126693MARKET INTERVENTION23/04/2025 05:15:54 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126683

Direction is cancelled from: 1715 hrs 23/04/2025

Manager NEM Real Time Operations
     
126692MARKET INTERVENTION23/04/2025 03:27:11 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126684

Direction is cancelled from: 1530 hrs 23/04/2025

Manager NEM Real Time Operations
     
126691MARKET INTERVENTION23/04/2025 12:38:14 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 24/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126690NON-CONFORMANCE23/04/2025 10:00:21 AM

NON-CONFORMANCE Region NSW1 Wednesday, 23 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 23 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JEMALNG1
Duration: 23/04/2025 08:50 to 23/04/2025 10:00
Amount: 38 MW
Constraint: NC-N_JEMALNG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126684MARKET INTERVENTION22/04/2025 02:21:02 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126643

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1530 hrs 23/04/2025.

The direction update is issued at 1420 hrs 22/04/2025.

Manager NEM Real Time Operations
     
126683MARKET INTERVENTION22/04/2025 02:22:28 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126644

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1715 hrs 23/04/2025.

The direction update is issued at 1420 hrs 22/04/2025.

Manager NEM Real Time Operations
     