127411MARKET INTERVENTION06/06/2025 03:58:42 PM

Cancellation - AEMO Intervention Event - SA region 05/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 05/06/2025

Refer to Market Notice 127388

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 06/06/2025.


Manager NEM Real Time Operations
     
127410MARKET INTERVENTION06/06/2025 03:58:31 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127407

Direction is cancelled from: 1600 hrs 06/06/2025

Manager NEM Real Time Operations
     
127408MARKET INTERVENTION06/06/2025 02:49:44 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1900 hrs 06/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 06/06/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
127407MARKET INTERVENTION06/06/2025 02:45:08 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127403

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 06/06/2025.

The direction update is issued at 1445 hrs 06/06/2025.

Manager NEM Real Time Operations
     
127403MARKET INTERVENTION05/06/2025 03:58:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127389

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 7/06/2025.

The direction update is issued at 1600 hrs 5/06/2025.

Manager NEM Real Time Operations
     
127397RESERVE NOTICE04/06/2025 07:40:01 PM

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127394 is cancelled at 1945 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127395RESERVE NOTICE04/06/2025 06:47:22 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127393 is cancelled at 1845 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127394RESERVE NOTICE04/06/2025 06:14:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 682 MW

Manager NEM Real Time Operations
     
127393RESERVE NOTICE04/06/2025 05:41:44 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1540 MW
The minimum capacity reserve available is 1540 MW