Reclassification of a Non-Credible Contingency Event: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV line and Strathmore-Clare South 7208 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV and Strathmore-Clare South 7208 132kV
Duration: 13/06/2021 07:06 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 13/06/2021
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 13/06/2021
At 0634hrs 13/06/2021 there was an unplanned outage of the Lismore 132kV SVC.
The following constraint set invoked at 0640 hrs 13/06/2021
N-LS_VC1
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/06/2021
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.86983 is cancelled at 1400 hrs 12/06/2021.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 12/06/2021 03:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 87032
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 12/06/2021 03:34
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 87031
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV
Cancellation time: 12/06/2021 03:34
Constraint set(s) revoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 87030
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 12/06/2021 02:31 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 12/06/2021 02:31 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV
Duration: 12/06/2021 02:31 until further notice
Constraint set(s) invoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side: